Starting Monday, Jan. 3, new traffic shifts and lane closures will take place on I-25 through Fountain.

Colorado Department of Transportation and Contractor SEMA Construction, Inc. will shift southbound I-25 over South Academy Boulevard (Exit 135), southbound I-25 over Clover Ditch (MP 131.2), and southbound I-25 over Dry Wash (MP 128.34). The traffic shifts will vary from 7 to 12 feet toward the outside and will require a nighttime single-lane closure. The traffic shifts in these three locations are to allow for crews to widen the bridge structures southbound over Clover Ditch and southbound I-25 over Dry Wash and begin the initial phases (demolition and reconstruction) of the I-25 bridges over South Academy.

There will also be daytime shoulder closures on eastbound and westbound South Academy Boulevard and nighttime left lane closures on South Academy Boulevard. Motorists should plan for lane closures, lane shifts, and striping crews with possible traffic delays to prepare for the bridge work.

In addition, work will continue on I-25 along a 7.5-mile segment between South Academy Boulevard and extending to the Santa Fe Avenue exit. Work will take place during evening and early morning hours, with lane closures on southbound I-25 to continue installation of permanent advance warning signs. Construction of northbound emergency pullouts (MP 129.6, 130.7, 132.7 and 133.7) with paving and barrier installation will require right-lane closures on northbound I-25.

TRAFFIC IMPACTS

Southbound I-25 nighttime single-lane closures and daytime shoulder closures and northbound I-25 nighttime right lane closures between approximately South Academy Boulevard and Santa Fe Avenue (Mile Point 135 - 127).

Monday, Jan. 3 – Thursday, Jan. 6, nighttime work hours approximately 6 p.m. – 6 a.m.

Friday, Jan. 7, nighttime work hours approximately 9 p.m. – 8 a.m.

Monday, Jan. 3 – Friday, Jan. 7, daytime work hours approximately 9 a.m. – 4 p.m.

- Speed limit reduction to 55 MPH during construction hours

- Eleven-foot width restrictions

- South Academy Boulevard near I-25 daytime right shoulder closures and left lane closures

Wednesday, Jan. 5 – Friday, Jan. 7, nighttime lane closure - work hours approximately 8 p.m. – 4:30 a.m.

Monday, Jan. 3, and Tuesday, Jan. 4, daytime shoulder closures - work hours approximately 9 a.m. – 5 p.m.

In the future, travelers can expect daytime and nighttime traffic impacts. Intermittent daytime and nighttime lane closures should be expected. Traffic fines will be doubled in the work zone. Motorists should slow down as they approach the work zones, drive with caution, allow extra space between vehicles, and give themselves extra travel time. Dates of work are weather permitting

This work is part of the Military Access, Mobility & Safety Improvement Project (MAMSIP). MAMSIP is comprised of four discrete road projects in the Pikes Peak region, all of which are strategically important in the movement of personnel and equipment between nationally significant military facilities.

 